Start of construction

08/2019

Construction time

2 years

Scope of services

New construction of a company building as general contractor in Ummeln

Planning services from service phase 5 (HOAI)

The building was erected as a reinforced concrete structure made of in-situ concrete, supplemented by walls made of sand-lime brickwork and precast concrete elements. The façade surface was constructed using facing brickwork. The roof was designed as a warm roof (flat roof without a ventilated air layer).

Turnkey development including outdoor facilities.

New construction of a warehouse

The warehouse was built as a steel hall construction on reinforced concrete foundations.

The wall cladding was made of trapezoidal sheet metal and the roof cladding for the monopitch roof was made of sandwich panels.

The floor was made of paving stones and a reinforced concrete base, smoothed and rubbed down

Work carried out on the company building:

Earthworks and complete demolition work on the existing buildings

Implementation planning incl. TGA

Screed and plaster work

Electrical and HLS installation

Joinery work

Roofing and waterproofing work

Tiles and floor coverings

Installation of a crane system

Construction of the complete outdoor facilities incl. fence system

Construction of the temporary operating site using a lightweight hall and a container system

Reinforced concrete and masonry work for the construction of the shell

Windows and doors made of thermally broken aluminum profiles

Drywall and system walls

Steel construction work for canopy and railings

Painting work

Metal construction and locksmith work for façade elements

Steel doors and gates, roller shutters

Work carried out Warehouse:

Earthworks

Construction of the reinforced concrete foundations and steel hall structure

Roof covering made of sandwich panel

Base made of smoothed and rubbed reinforced concrete and paving stones

Implementation planning incl. electrical

Plumbing and drainage work

Trapezoidal sheet metal wall cladding

Installation of sectional doors with electric drive and wicket door

Execution of electrical installation

Scaffolding work and fall protection