Relocation of the Thyssengas pipeline 070-000 in the Duisburg Masurensee area

References

Relocation of the Thyssengas pipeline 070-000 in the Duisburg Masurensee area

Client

Thyssengas GmbH

Contact person

Dipl.-Ing. Udo Mers

Start of construction

03/2022

Construction time

7 months

Scope of services

GEBAG Duisburger Baugesellschaft mbH is planning a land development project in the Wedau district of Duisburg. The “6-Seen-Wedau” project is one of the largest urban development projects in NRW. The plan is to build 3,000 residential units here.

Line 70 of Thyssengas runs in the area of the planned development site, which therefore had to be rerouted over a length of 450m.

Work carried out:

Civil engineering and pipeline construction work, relining incl. Pressure test gas pipe DN 600, DP 100

Partially complex shoring work. Excavations up to 5 m deep

Partial restoration of the paved surfaces

Elaborate dewatering incl. Filter systems

Integration into the gas-conducting system