Valve stations Ochtrup Wester II

References

Valve stations Ochtrup Wester II

Client

Thyssengas GmbH

Contact person

Mr. Dipl.-Ing. Udo Mers

Start of construction

october 2018

Construction time

4 months

Scope of services

In order to optimize the four valve groups at the Thyssengas-Ochtrup Wester station and to maintain safe pipeline operation, we are carrying out a complete expansion and new construction of all existing valve stations.

Technical specification:

Pipe diameter: DN 200 to DN 600

MOP: 70 bar

Material: Material groups 1 and 2

WORK CARRIED OUT:

Earthworks

Shoring

Prefabrication, testing and re-sheathing of slide gate assemblies and tie-in structures

Exposure of all existing pipes using a suction excavator

Dewatering

Backfilling the excavation pit partly with liquid soil