Start of construction

05/2024

Construction time

7 months

Scope of services

As part of the project, all piping, civil engineering, and concrete work was carried out for the reconstruction and new construction of interconnections for the EUGAL, OPAL, and JAGAL long-distance natural gas pipeline systems, as well as for the FLOW project at the Radeland site. The work was carried out in a joint venture with PPS.

Work carried out:

Civil engineering work involving approximately 30,000 m³ of excavated soil

Excavation of foundation pits up to 6.5 m deep

Concrete work for foundations and foundation slabs with a total volume of approximately 300 m³

Completion of 85 welds in DN 1400 and 137 welds in DN 1200

Conducting pressure tests and coating work

Manufacture of five culverts with nominal diameters up to DN 1400

Shoring work using sheet pile walls

Pipeline construction work up to DN 1400 and DP 100

Restoration of paved surfaces, including paving and curbing work