Client

Erdgas Münster GmbH

Contact person

RNW IWS Frank Kessens

Start of construction

10/2019

Construction time

4 months

Scope of services

Erdgas Münster GmbH is adjusting gas flows at some stations in order to optimize domestic production diversion.

The new stations were prefabricated at the plant in Neuenhaus.

Scope of services:

Conversion of the Twist, Rühlermoor I, Rühlermoor II and Annaveen natural gas stations.

WORK CARRIED OUT:

Civil engineering and pipeline construction work, relining incl. Pressure test

Closed dewatering

Integration into the gas-conducting system

Pipeline construction work in plant construction Nominal diameters DN 50 to DN 250 / DP100

Coating work