LAYING OF A NEW GAS TRANSPORT PIPELINE FROM OBEROHE TO POITZEN

References

LAYING OF A NEW GAS TRANSPORT PIPELINE FROM OBEROHE TO POITZEN

Client

Nowega GmbH

Contact person

M. Eng. Bianca Meyerink

Start of construction

04/2020

Construction time

5 months

Scope of services

New laying of gas transport pipeline no. 309 (DN 150 DP 100) from Oberohe to Poitzen over a length of approx. 6 km.

WORK CARRIED OUT:

Civil engineering and pipeline construction work, relining incl. Pressure test

Crossings of other road junctions using the HDD method, lengths from 160 m to 340 m and pile driving for short lengths up to 20 m

Construction of site roads

Integration into the gas-conducting system

Crossings of biotopes using the HDD method. Lengths 570 m and 685 m

Closed dewatering