New construction of a production facility as 2nd construction phase in St. Georgen (Black Forest)

References

New construction of a production facility as 2nd construction phase in St. Georgen (Black Forest)

Client

ebm-papst St. Georgen GmbH & Co. KG

Contact person

Dipl.-Ing. Uwe Lammers

Start of construction

06/2016

Construction time

16 months

Scope of services

Construction of the entire technical facilities, foundations, buildings, infrastructure and roads.

2-storey administration building with 1,345 m² of usable space

2-storey logistics building with social rooms on the 1st floor with 2,619 m² + 506 m² usable space

Assembly hall with 4,298 m² usable space

Equipment building with 1,083 m² usable space

Work carried out:

General contractor for the construction (excluding electrical work, TGA) of the building.

Laying the supply and disposal lines incl. earthworks.

Production of a concrete floor with ESD coating (electrically dissipative) or an industrial floor with hard material layer (wear resistance 3 cm³/50 cm²) and integrated industrial surface heating.

Installation of the thermal wall elements with corrugated profile on the outside and top finish using Domico Planum.

Execution of screed, floor covering, tiling, dry construction, locksmith and painting work.

Construction of a gravel base course below the concrete base and foundation work.

Construction of the fire walls using aerated concrete elements.

Installation of an aluminum mullion and transom façade.

Execution of the trapezoidal sheet metal and roof waterproofing work with corresponding continuous rooflight constructions on prestressed concrete trusses.

Reinforced concrete and masonry work.

Installation of the thermal cavity walls and prestressed concrete hollow core slab.