NEW CONSTRUCTION OF SILO 5 IN KARUP/DENMARK

References

NEW CONSTRUCTION OF SILO 5 IN KARUP/DENMARK

Client

AKK – Karup Kartoffelmelfabrik

Contact person

Dipl.-Ing. Bertram Vocks

Start of construction

02/2021

Construction time

3 months

Scope of services

Construction of all foundation and building construction work for the new silo 5 in Karup/Denmark.

The building has a floor area of approx. 2,300 m² and reaches a height of 55 m.

A tunnel was built under the silo to reach the conveyor system at the foot of the central column.

The approx. 1,900 m³ floor slab was concreted in one section in just 16 hours.

The 55-meter-high walls were then constructed in 17 days and nights using 3,000 m³ of concrete with the aid of slipforming.

Work carried out:

Earthworks incl. Partial soil replacement

Production of a basement tunnel with anchor ring for the Central Collumn

Production of the silo walls in slipform construction

Foundation work at various levels

Flat foundation with an 80 cm thick reinforced concrete base slab