OGE DOROMI

References

OGE DOROMI

Client

Open Grid Europe GmbH

Contact person

Mr. Dipl.-Ing. Udo Mers

Start of construction

February 2018

Construction time

8 months

Scope of services

Piping system L 13/4 or L 13/4/50

Replacement of fittings

Separation of the printing systems

19 pieces bindings for slider groups

Installation of emergency connections and additional switching options

Relocation of various pipes and removal of old taps

Fittings and auxiliary lines.

Technical specification:

Pipe diameter: up to DN 400

MOP: 50 bar

Material: Material groups 1 and 2

WORK CARRIED OUT:

Earthworks

Dewatering

Integration of the aforementioned slide groups and tie-in components in a relatively short period of time

Shoring

Prefabrication, testing and re-coating of the slide assemblies and binding components